Eight
rules to follow:
- Substation Capacity and Short Circuit Current Capacity (As per GERC)
- Substation Capacity and Short Circuit Current Capacity (As per Central Electricity Authority)
- Minimum Ground Clearance and Fault Clearing Time
- Busbar Ampere Rating
- Busbar Spacing
- Sound Level of Diesel Generator (ANSI 89.2 and NEMA 51.20)
- IR Value of Transformer
- Standard Size of MCB, MCCB, ELCB, RCCB, SFU and Fuse
1.
Substation Capacity and Short Circuit Current Capacity
As per GERC
|
||
Voltage
|
Sub
Station Capacity
|
Short
Circuit Current
|
400
KV
|
Up
to 1000 MVA
|
40
KA (1 to 3 Sec)
|
220
KV
|
Up
to 320 MVA
|
40
KA (1 to 3 Sec)
|
132
KV
|
Up
to 150 MVA
|
32
KA (1 to 3 Sec)
|
66
KV
|
Up
to 80 MVA
|
25
KA (1 to 3 Sec)
|
33
KV
|
1.5
MVA to 5 MVA
|
35
KA (Urban) (1 to 3 Sec)
|
11
KV
|
150
KVA to 1.5 MVA
|
25
KA (Rural) (1 to 3 Sec)
|
415
V
|
6
KVA to 150 KVA
|
10
KA (1 to 3 Sec)
|
220
V
|
Up
to 6 KVA
|
6
KA (1 to 3 Sec)
|
2.
Substation Capacity and Short Circuit Current Capacity
As per Central Electricity Authority
|
||
Voltage
|
Sub
Station Capacity
|
Short
Circuit Current
|
765
KV
|
4500
MVA
|
31.5
KA for 1 Sec
|
400
KV
|
1500
MVA
|
31.5
KA for 1 Sec
|
220
KV
|
500
MVA
|
40
KA for 1 Sec
|
110/132
KV
|
150
MVA
|
40
KA or 50 KA for 1 Sec
|
66
KV
|
75
MVA
|
40
KA or 50 KA for 1 Sec
|
3.
Minimum Ground Clearance and Fault Clearing Time
Voltage
|
Min. Ground Clearance
|
Fault Clear Time
|
400
KV
|
8.8
Meter
|
100
mille second
|
220
KV
|
8.0
Meter
|
120
mille second
|
132
KV
|
6.1
Meter
|
160
mille second
|
66
KV
|
5.1
Meter
|
300
mille second
|
33
KV
|
3.7
Meter
|
–
|
11
KV
|
2.7
Meter
|
–
|
For Phase Busbar
|
Aluminium
130 Amp / Sq.cm or 800Amp / Sq.inch.
|
For Phase Busbar
|
Copper
160 Amp / Sq.cm or 1000Amp / Sq.inch
|
For Neutral Busbar
|
Same
as Phase Busbar up to 200 Amp than Size of Neutral Busbar is at least half of
Phase Busbar.
|
5.
Busbar Spacing
Between Phase and Earth
|
26mm
(Min)
|
Between Phase and Phase
|
32mm
(Min)
|
Busbar Support between Two
Insulator
|
250mm.
|
6.
Sound Level of Diesel Generator (ANSI 89.2 and NEMA 51.20)
KVA
|
Max. Sound Level
|
<9
KVA
|
40
DB
|
10
KVA to 50 KVA
|
45
DB
|
51
KVA to 150 KVA
|
50
DB
|
151
KVA to 300 KVA
|
55
DB
|
301
KVA to 500 KVA
|
60
DB
|
7.
IR Value of Transformer
IR Value of Transformer
|
|||
Voltage
|
30°C
|
40°C
|
50°C
|
>66KV
|
600MΩ
|
300MΩ
|
150MΩ
|
22KV
to 33KV
|
500MΩ
|
250MΩ
|
125MΩ
|
6.6KV
to 11KV
|
400MΩ
|
200MΩ
|
100MΩ
|
<6.6KV
|
200MΩ
|
100MΩ
|
50MΩ
|
415V
|
100MΩ
|
50MΩ
|
20MΩ
|
MCB, MCCB, ELCB, RCCB, SFU, Fuse – Standard Ratings
|
|
MCB
|
Up to 63 Amp (80Amp and 100 Amp
a per Request)
|
MCCB
|
Up to 1600 Amp (2000 Amp as per
Request)
|
ACB
|
Above 1000 Amp
|
MCB Rating
|
6A,10A,16A,20A,32A,40A,50A,63A
|
MCCB Rating
|
0.5A,1A,2A,4A,6A,10A,16A,20A,32A,40A,50A,63A,80A,100A
(Domestic Max 6A)
|
RCCB/ELCB
|
6A,10A,16A,20A,32A,40A,50A,63A,80A,100A
|
Sen. of ELCB
|
30ma (Domestic),100ma
(Industrial),300ma
|
DPIC (Double Pole Iron Clad) main
switch
|
5A,15A,30 A for 250V
|
TPIC (Triple Pole Iron Clad) main
switch
|
30A, 60A, 100A, 200 A For 500 V
|
DPMCB
|
5A, 10A, 16A, 32A and 63 A for
250V
|
TPMCCB
|
100A,200A, 300Aand 500 A For 660 V
|
TPN main switch
|
30A, 60A, 100A, 200A, 300 A For
500 V
|
TPNMCB
|
16A, 32A,63A For 500 V, beyond
this TPNMCCB: 100A, 200A, 300A, 500 A For 660 V
|
TPN Fuse Unit (Rewirable)
|
16A,32A,63A,100A,200A
|
Change over switch (Off Load)
|
32A,63A,100A,200A,300A,400A,630A,800A
|
SFU (Switch Fuse Unit)
|
32A,63A,100A,125A,160A,200A,250A,315A,400A,630A
|
HRC Fuse TPN (Bakelite)
|
125A,160A,200A,250A,400A.630A
|
HRC Fuse DPN (Bakelite)
|
16A,32A,63A
|
MCB/MCCB/ELCB Termination Wire / Cable
|
|
Up to 20A MCB
|
Max. 25 Sq.mm
|
20A to 63A MCB
|
Max. 35 Sq.mm
|
MCCB
|
Max. 25 Sq.mm
|
6A to 45A ELCB
|
16 Sq.mm
|
24A to 63A ELCB
|
35 Sq.mm
|
80A to 100A ELCB
|
50 Sq.mm
|
Size
of Capacitor for Power Factor Correction
For Motor
|
|
Size
of Capacitor = 1/3 Hp of Motor ( 0.12x KW of Motor)
|
|
For Transformer
|
|
< 315 KVA
|
5%
of KVA Rating
|
315 KVA to 1000 KVA
|
6%
of KVA Rating
|
>1000 KVA
|
8%
of KVA Rating
|
Earthing
Resistance value
Earthing Resistance Value
|
|
Power Station
|
0.5
Ω
|
Sub Station Major
|
1.0
Ω
|
Sub Station Minor
|
2.0
Ω
|
Distribution Transformer
|
5.0
Ω
|
Transmission Line
|
10
Ω
|
Single Isolate Earth Pit
|
5.0
Ω
|
Earthing Grid
|
0.5
Ω
|
As per NEC Earthing Resistance
should be <5.0 Ω
|
Voltage
Limit (As per CPWD & KEB)
Voltage Limit (As Per CPWD)
|
|
240V
|
<
5 KW
|
415V
|
<100
KVA
|
11KV
|
<3
MVA
|
22KV
|
<6
MVA
|
33KV
|
<12
MVA
|
66KV
|
<20
MVA
|
110KV
|
<40
MVA
|
220KV
|
>40
MVA
|
Voltage
Variation
> 33 KV
|
(-)
12.5% to (+) 10%
|
< 33 KV
|
(-)
9% to (+) 6%
|
(-)
6% to (+) 6%
|
Insulation
Class
Insulation
|
Temperature
|
Class A
|
105°C
|
Class E
|
120°C
|
Class B
|
130°C
|
Class F
|
155°C
|
Class H
|
180°C
|
Class N
|
200°C
|
Standard
Voltage Limit
Voltage
|
IEC (60038)
|
IEC (6100:3.6)
|
Indian Elect. Rule
|
ELV
|
<
50 V
|
||
LV
|
50
V to 1 KV
|
<=1
KV
|
<
250 V
|
MV
|
<=
35 KV
|
250
V to 650 V
|
|
HV
|
>
1KV
|
<=
230 KV
|
650
V to 33 KV
|
EHV
|
>
230 KV
|
>
33 KV
|
Standard
Electrical Connection (As per GERC)
As per Type of Connection
|
|
Connection
|
Voltage
|
LT Connection
|
<=440V
|
HT connection
|
440V
to 66KV
|
EHT connection
|
>=
66KV
|
As per Electrical Load Demand
|
|
Up 6W Load demand
|
1
Phase 230V Supply
|
6W to 100KVA(100KW)
|
3
Phase 440V Supply
|
100KVA to 2500KVA
|
11KV,22KV,33KV
|
Above 2500KVA
|
66KV
|
HT Connection Earthing
|
|
H.T Connection’s Earthing Strip
|
20mmX4mm
Cu. Strip
|
CT & PT bodies
|
2Nos
|
PT Secondary
|
1Nos
|
CT Secondary
|
1Nos
|
I/C and O/G Cable+ Cubicle Body
|
2Nos
|
Standard
Meter Room Size (As per GERC)
Meter Box Height
|
Upper level does not beyond 1.7
meter and Lower level should not below 1.2 meter from ground.
|
Facing of Meter Box
|
Meter Box should be at front area
of Building at Ground Floor.
|
Meter Room / Closed Shade
|
4 meter square Size
|
Electrical Load
as per Sq.ft Area (As per DHBVN)
Sq.ft Area
|
Required Load (Connected)
|
< 900 Sq.ft
|
8
KW
|
901 Sq.ft to 1600 Sq.ft
|
16
KW
|
1601 Sq.ft to 2500 Sq.ft
|
20
KW
|
> 2500 Sq.ft
|
24
KW
|
For Flats :100 Sq.ft / 1 KW
|
|
For Flats USS /TC: 100 Sq.ft / 23
KVA
|
For Domestic Load
|
500 watt per 100 Sq. foot of the constructed area.
|
For Commercial
|
1500 watt per 100 Sq. foot of the constructed area
|
Other Common Load
|
For lift, water lifting pump, streetlight if any,
corridor/campus lighting and other common facilities, actual load shall be
calculated
|
Staircase Light
|
11KW/Flat Ex: 200Flat=200×11=2.2KW
|
Sanctioned Load for Building
|
|
Up to 50 kW
|
The L.T. existing mains shall be strengthened.
|
50 kW to 450 kW (500 kVA)
|
11 kV existing feeders shall be extended if spare capacity
is available otherwise, new 11 kV feeders shall be constructed.
|
450 kW to 2550 kW (3000 kVA)
|
11 kV feeder shall be constructed from the nearest 33 kV
or 110 kV substation
|
2550 kW to 8500 kW (10,000 kVA)
|
33kV feeder from 33 kV or 110 kV sub station
|
8500 kW (10,000 kVA)
|
110 kV feeder from nearest 110 kV or 220 kV sub-station
|
Contracted Load in case of High-rise Building Useful
Electrical
Equations
- For Sinusoidal Current: Form Factor = RMS Value/Average Value = 1.11
- For Sinusoidal Current: Peak Factor = Max Value/RMS Value = 1.414
- Average Value of Sinusoidal Current (Iav) = 0.637 x Im (Im = Max.Value)
- RMS Value of Sinusoidal Current (Irms) = 0.707 x Im (Im = Max.Value)
- A.C Current = D.C Current/0.636.
- Phase Difference between Phase = 360/ No of Phase (1 Phase=230/1=360°, 2 Phase=360/2=180°)
- Short Circuit Level of Cable in KA (Isc)
=
(0.094 x Cable Dia in Sq.mm) /√ Short Circuit Time (Sec) - Max.Cross Section Area of Earthing Strip (mm2) = √(Fault Current x Fault
Current x Operating Time of Disconnected Device ) / K
K = Material Factor, K for Cu = 159, K for Al = 105, K for steel = 58 , K for GI = 80 - Most Economical Voltage at given Distance = 5.5 x √ ((km/1.6) + (kw/100))
- Cable Voltage Drop (%) =
(1.732 x current x (RcosǾ+jsinǾ) x 1.732 x Length (km) x 100) / (Volt(L-L) x Cable Run. - Spacing of Conductor in Transmission Line (mm) = 500 + 18 x (P – P Volt) + (2 x (Span in Length)/50).
- Protection radius of Lighnting Arrestor = √h x
(2D-h) + (2D+L).
Where h= height of L.A, D-distance of equipment (20, 40, 60 Meter), L=V x t (V=1m/ms, t=Discharge Time). - Size of Lightning Arrestor = 1.5x Phase to Earth Voltage or 1.5 x (System Voltage/1.732).
- Maximum Voltage of the System = 1.1xRated Voltage (Ex. 66KV = 1.1 × 66 = 72.6KV)
- Load Factor = Average Power/Peak Power
- If Load Factor is 1 or 100% = This is best situation for System and Consumer both.
- If Load Factor is Low (0 or 25%) = you are paying maximum amount of KWH consumption. Load Factor may be increased by switching or use of your Electrical Application.
- Demand Factor = Maximum Demand / Total Connected Load (Demand Factor <1)
- Demand factor should be applied for Group Load
- Diversity Factor =
Sum of Maximum Power Demand / Maximum Demand (Demand Factor >1)
Diversity factor should be consider for individual Load - Plant Factor (Plant Capacity) = Average Load / Capacity of Plant
- Fusing Factor = Minimum Fusing Current / Current Rating (Fusing Factor>1).
- Voltage Variation (1 to 1.5%) = ((Average Voltage – Min
Voltage) x 100)/Average Voltage
Ex: 462V, 463V, 455V, Voltage Variation= ((460 – 455) x 100)/455 = 1.1%. - Current Variation (10%) = ((Average Current – Min
Current) x 100)/Average Current
Ex: 30A,35A,30A, Current Variation = ((35-31.7) x 100)/31.7 = 10.4% - Fault Level at TC Secondary
= TC (VA) x 100 / Transformer Secondary (V) x Impedance (%) - Motor Full Load Current = Kw /1.732 x KV x P.F x Efficiency
No comments:
Post a Comment